Time and Work Concepts and Shortcuts: Solved Examples for Competitive Exams

Learn how to model Time and Work questions, select the right shortcut, and solve combined-work, efficiency, worker-hour, and changing-schedule problems accurately.

KnowledgeGate Team

Exam prep & CS education

Updated 7 Nov 20265 min read
Time and Work Concepts and Shortcuts: Solved Examples for Competitive Exams

Time and Work questions often look unrelated because one asks about two people, another changes the number of workers, and a third makes workers alternate. Underneath, each one uses the same three ideas: total work, rate, and time. The reliable approach is to choose between fractions, LCM units, and ratios, then track exactly who works during each interval.

Build every Time and Work problem from work, rate, and time

Start with one identity:

Work = Rate x Time

If A completes a fixed job in 12 days, A completes 1/12 of the job per day. If B takes 18 days, B's daily rate is 1/18. Rate is also called efficiency. For the same fixed job, a higher efficiency produces a shorter completion time.

This model assumes that the job size is fixed and each stated rate stays constant. Add rates only when the workers or machines are active together. Once somebody leaves, that rate must leave the calculation too.

The fraction method treats the whole job as 1. It is compact for a clean, one-step combination. The LCM-units method chooses a convenient integer as total work. It usually makes joining, leaving, and alternate-day schedules easier to see.

Use LCM units for combined work

Suppose A takes 12 days and B takes 18 days.

  1. Set total work to LCM(12, 18) = 36 units.

  2. A's rate is 36/12 = 3 units per day.

  3. B's rate is 36/18 = 2 units per day.

  4. Together, their rate is 3 + 2 = 5 units per day.

  5. Required time is 36/5 = 7 1/5 days.

That means seven complete working days and one-fifth of another working day. The fraction check gives the same answer:

1/12 + 1/18 = 3/36 + 2/36 = 5/36

So the time is 1 / 5/36 = 36/5 days. Never add 12 + 18 to find a combined time. Completion times do not add, rates do.

Table showing a 36-unit job: A works at 3 units per day, B at 2, and together finish in 7 1/5 days.

Turn efficiency ratios into time ratios

For a fixed job, efficiency and time are inversely proportional. If the efficiency ratio A:B is 3:2, the time ratio A:B is 2:3. Copying 3:2 directly as the time ratio reverses the meaning.

Suppose B takes 15 days and the efficiency ratio A:B is 3:2. B's 15 days correspond to three parts in the time ratio 2:3, so A takes:

15 x 2/3 = 10 days

Their rates are 1/10 and 1/15. Together:

1/10 + 1/15 = 3/30 + 2/30 = 1/6

Therefore, they finish together in 6 days.

Percentage statements use the same idea. If A is 25% more efficient than B, their rates are 125:100 = 5:4, so their times are 4:5. If B needs 20 days, A needs 20 x 4/5 = 16 days.

Scale workers, hours, and days without losing the assumptions

For equal workers with constant productivity:

workers x days x hours per day x productivity = fixed work

Suppose 12 workers complete a job in 15 days while working 6 hours per day. The job requires:

12 x 15 x 6 = 1080 worker-hours

Now use 18 equally productive workers for 5 hours per day. Their daily capacity is 18 x 5 = 90 worker-hours, so they need:

1080/90 = 12 days

This shortcut fails if worker productivity differs or the amount of work changes.

Work contribution is also different from clock time. X works for 4 days at 3 units per day, contributing 4 x 3 = 12 units. Y works for 5 days at 2 units per day, contributing 5 x 2 = 10 units. A reward based strictly on contribution is divided in the ratio 12:10 = 6:5, not 4:5 and not 3:2.

Handle joining, leaving, and alternate-day schedules as a timeline

Return to the 36-unit job. A and B work together for 4 days at 5 units per day, so they complete 4 x 5 = 20 units. B then leaves. The remaining work is 36 - 20 = 16 units, which A completes at 3 units per day in 16/3 = 5 1/3 days. Total elapsed time is:

4 + 5 1/3 = 9 1/3 days

Timeline showing A and B complete 20 of 36 units in four days, then A finishes the remaining work alone in 9 1/3 days.

For an alternate-day example, let A finish alone in 10 days and B in 15 days. Choose 30 units of total work. A completes 3 units per day and B completes 2.

If A starts, one two-day cycle completes 3 + 2 = 5 units. Five cycles complete 25 units in 10 days. A completes 3 more units on day 11, leaving 2 units. B completes those 2 units on day 12. The answer is 12 days. Always note who starts because reversing the order can change the finishing day.

Choose the fastest safe shortcut under time pressure

Use fractions for one clean rate combination. Use LCM units when the completion times have a manageable LCM or when the schedule changes. Use ratios when the question gives relative efficiency. If the LCM becomes awkward, keep total work as 1 instead of forcing large integers.

Apply three quick checks before accepting an answer:

  • With positive rates, a combined time must be shorter than the faster individual's time.

  • A more efficient worker must take less time for the same job.

  • Completed work across every phase must equal the selected total work.

A compact scratch table with worker, time, rate, and active interval is usually enough. A useful shortcut reduces conversions. It does not skip the model.

Recognise question shapes and avoid common traps

Common forms include individual and combined work, efficiency comparisons, joining or leaving, alternate days, worker-hour scaling, machine productivity, and contribution-based sharing. The Placement Preparation category places these questions within the wider aptitude syllabus.

Most errors come from adding completion times instead of rates, treating efficiency and time as directly proportional, forgetting who starts an alternating schedule, using worker-hours despite unequal productivity, or retaining a worker's rate after departure. Also avoid rounding a fractional day until you have checked whether the question asks for exact time, completed days, or the day on which work finishes.

For a wider topic map and weekly plan, use Aptitude for Placements. Readers preparing specifically for SSC CGL can connect the same rate methods to the broader plan in SSC CGL Quant Strategy. For any specific exam, confirm its current pattern and instructions in the official notification.

The short version: revise, then practise by method

Choose a total amount of work, turn every completion time into a rate, and add rates only during shared intervals. After each phase, subtract completed work from the total. When converting efficiency into time, invert the ratio.

After the examples, practise in a deliberate sequence: solve 5 basic rate questions, 5 combined-work questions, then 5 schedule-change questions. For each miss, record whether the cause was setup, arithmetic, or a misread timeline.

For placement-focused aptitude, continue with Aptitude for Placement. For GATE-focused practice, use Aptitude for GATE. Pick the track that matches your goal, but keep the method constant: model the work first, then calculate.