A can complete a piece of work in 8 days, and B can complete the same work in…

2024

A can complete a piece of work in 8 days, and B can complete the same work in 10 days. If A and B work together, how long will they take to complete the work?

Answer: B. \(4\frac{4}{9}\) daysConceptA worker's one-day work rate is the reciprocal of the time taken to complete the whole job alone. When workers contribute independently to the same job…

  1. A.

    6 days

  2. B.

    \(4\frac{4}{9}\) days

  3. C.

    \(4\frac{1}{5}\) days

  4. D.

    \(5\frac{1}{2}\) days

Attempted by 2 students.

Show answer & explanation

Correct answer: B

Concept

A worker's one-day work rate is the reciprocal of the time taken to complete the whole job alone.

When workers contribute independently to the same job at the same time, their work rates add, and the completion time is the reciprocal of the combined rate.

Application

  1. Let the total work be 1 unit. The one-day rates of A and B are \(\frac{1}{8}\) and \(\frac{1}{10}\) of the work.

  2. Their combined rate is \(\frac{1}{8}+\frac{1}{10}=\frac{5+4}{40}=\frac{9}{40}\) of the work per day.

  3. Therefore, the required time is \(1\div\frac{9}{40}=\frac{40}{9}\) days.

  4. Converting the improper fraction gives \(\frac{40}{9}=4\frac{4}{9}\) days.

Cross-check

In \(\frac{40}{9}\) days, the combined work is \(\frac{40}{9}\times\frac{9}{40}=1\) complete job, so the result is consistent.

Result

A and B complete the work in \(4\frac{4}{9}\) days.

Explore the full course: Uptet Paper 1

Loading lesson…