It was estimated that 52 men can complete a strip in a newly constructed…
GATE · 2020 · ME · Set 2 · General Aptitude
It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?
- A.
3 days
- B.
5 days
- C.
10 days
- D.
13 days