A software project plan has identified ten tasks with dependencies as given…
PYQ GATE 2008
A software project plan has identified ten tasks with dependencies as given below:
Task Depends on
T1 -
T2 T1
T3 T1
T4 T1
T5 T2
T6 T3
T7 T3, T4
T8 T4
T9 T5, T7, T8
T10 T6, T9
Answer the following questions:
(Q1) What is the maximum number of tasks that can be done concurrently?
(Q2) What is the minimum time required to complete the project, assuming that each task requires one time unit and there is no restriction on the number of tasks that can be done in parallel?