Assume that the delivered lines of code L of a software are related to the…

PYQ GATE 2004

Assume that the delivered lines of code L of a software are related to the effort E (in person-months) and duration t (in calendar months) by the relation:

L = P × (E/B)^(1/3) × t^(4/3)

where P and B are constants for the software process and skills factor. For a software project, the effort was estimated to be 20 person-months and the duration was estimated to be 8 months. However, the customer asked the project team to complete the software project in 4 months. What would be the required effort in person-months?

  1. A.

    10

  2. B.

    40

  3. C.

    160

  4. D.

    320

Attempted by 10 students.