A software project has four phases P1, P2, P3 and P4. P1 is the first phase…

PYQ GATE 2006

A software project has four phases P1, P2, P3 and P4. P1 is the first phase and must be completed before any other phase can start. Phases P2 and P3 can be executed in parallel. Phase P4 cannot start until both P2 and P3 are completed.

The optimistic, most likely, and pessimistic estimates of the phase completion times in days for P1, P2, P3 and P4 are respectively:
P1: (11, 15, 25)
P2: (7, 8, 15)
P3: (8, 9, 22)
P4: (3, 8, 19)

The costs in rupees per day of crashing the expected phase completion times for P1, P2, P3 and P4 are respectively 100, 2000, 50 and 1000. Assume that the expected phase completion times cannot be crashed below the respective most likely times.

The minimum and maximum amounts in rupees that can be spent on crashing so that all paths are critical are respectively:

  1. A.

    100 and 1000

  2. B.

    100 and 1200

  3. C.

    150 and 1200

  4. D.

    200 and 2000

Attempted by 4 students.