Consider the CPM activity chart where an arc connecting two milestones is…
PYQ GATE 2007
Consider the CPM activity chart where an arc connecting two milestones is labeled with a task identifier and the time taken in days. For example in order to go from A to B, task T1 takes 180 days. A dashed line depicts an additional dependency that is equivalent to a zero time task.

The set of activities that lie on the critical path are
- A.
T1, T2, T8, T10
- B.
T1, T3, T8, T10
- C.
T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
- D.
T1, T4, T5, T7, T8, T10