A software project involves execution of 5 tasks T₁, T₂, T₃, T₄ and T₅ of duration 10, 15, 18, 30 and 40 days, respectively. T₂ and T₄ can start only after T₁ completes. T₃ can start after T₂ completes. T₅ can start only after both T₃ and T₄ complete. What is the slack time of task T₃ in days?
- A.
0
- B.
3
- C.
18
- D.
30