A software project has four phases P1, P2, P3 and P4. P1 is the first phase…
PYQ GATE 2006
A software project has four phases P1, P2, P3 and P4. P1 is the first phase and must be completed before any other phase can start. Phases P2 and P3 can be executed in parallel. Phase P4 cannot start until both P2 and P3 are completed.
The optimistic, most likely, and pessimistic estimates of the phase completion times in days for P1, P2, P3 and P4 are respectively:
P1: (11, 15, 25)
P2: (7, 8, 15)
P3: (8, 9, 22)
P4: (3, 8, 19)
The critical path for the above project and the slack of P2 are, respectively:
- A.
P1-P2-P4, 1 day
- B.
P1-P3-P4, 1 day
- C.
P1-P3-P4, 2 days
- D.
P1-P2-P4, 2 days