5 pumps, working 18 hours a day, can empty a tank in 12 days. How many hours a…
2024
5 pumps, working 18 hours a day, can empty a tank in 12 days. How many hours a day must 6 pumps operate to empty a tank in 9 days?
Answer: B. 20 hours — Concept — The amount of work needed to empty the tank is a fixed quantity, and it can be measured in pump-hours: work = (number of pumps) × (hours worked each…
- A.
19 hours
- B.
20 hours
- C.
21 hours
- D.
22 hours
Attempted by 2 students.
Show answer & explanation
Correct answer: B
Concept — The amount of work needed to empty the tank is a fixed quantity, and it can be measured in pump-hours: work = (number of pumps) × (hours worked each day) × (number of days). Because the very same tank is emptied in both arrangements, that product cannot change, which gives the chain rule:
M1 × H1 × D1 = M2 × H2 × D2
where M is the number of pumps, H the hours worked each day, and D the number of days.
Application
First arrangement: 5 pumps × 18 hours a day × 12 days = 1080 pump-hours of work empty the tank.
Second arrangement: 6 pumps run for 9 days at H hours a day, supplying 6 × H × 9 = 54H pump-hours.
The tank emptied is the same, so the two amounts of work are equal: 54H = 1080.
Dividing both sides by 54 gives H = 1080 ÷ 54 = 20.
Cross-check
Substituting back: 6 × 20 × 9 = 1080 pump-hours, exactly the work obtained from 5 × 18 × 12.
Proportion method: adding pumps reduces the daily hours in the ratio 5 : 6, and shortening the schedule raises them in the ratio 12 : 9, so H = 18 × (5/6) × (12/9) = 15 × (12/9) = 20 — the same value.
Hence 6 pumps must work 20 hours a day to empty the tank in 9 days.