Ten people working 6 hours per day can complete a task in 8 days. How many…

2026

Ten people working 6 hours per day can complete a task in 8 days. How many people are needed to complete the same task in 4 days if they work 8 hours per day?

Answer: A. 15ConceptFor a fixed task, total work is measured in person-hours: number of people × hours worked per day × number of days. When the task is unchanged, the…

  1. A.

    15

  2. B.

    10

  3. C.

    18

  4. D.

    5

Attempted by 58 students.

Show answer & explanation

Correct answer: A

Concept

For a fixed task, total work is measured in person-hours: number of people × hours worked per day × number of days.

When the task is unchanged, the total person-hours remain constant; changes in daily hours or days must be balanced by the number of people.

Application

  1. The original team performs 10 × 6 × 8 = 480 person-hours of work.

  2. In the new schedule, each person works 8 × 4 = 32 hours in total.

  3. Let p be the required number of people. Then p × 32 = 480, so p = 480 ÷ 32 = 15.

Cross-check

With 15 people, the available work is 15 × 8 × 4 = 480 person-hours, exactly equal to the original workload. Therefore, 15 people are needed.