Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours…

2024

Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours a day, 15 persons can do the same work in:

Answer: C. 30 daysConceptWhen one and the same job is finished under two different working arrangements, the total amount of labour the job demands does not change. Measuring…

  1. A.

    28 days

  2. B.

    29 days

  3. C.

    30 days

  4. D.

    32 days

Attempted by 4 students.

Show answer & explanation

Correct answer: C

Concept

When one and the same job is finished under two different working arrangements, the total amount of labour the job demands does not change. Measuring that labour in man-hours turns this into a single invariant: persons × hours worked per day × days = total man-hours.

Hence M1H1D1 = M2H2D2. The number of days is inversely proportional to the product of the number of persons and the hours each of them works per day.

Application

  1. First arrangement: 12 persons work 9 hours a day for 25 days.

  2. Total work = 12 × 9 × 25 = 2700 man-hours. This total is fixed by the job itself, so it must also hold for the second arrangement.

  3. Second arrangement: 15 persons work 6 hours a day, so together they supply 15 × 6 = 90 man-hours each day.

  4. Let D be the number of days required. Equating the labour supplied to the labour demanded: 90 × D = 2700.

  5. D = 2700 ÷ 90 = 30.

Cross-check

The same figure follows from proportionality alone, without ever computing the total.

  • Persons rise from 12 to 15, a factor of 15/12 = 5/4. More workers shorten the time, so the days get multiplied by the reciprocal 4/5.

  • Hours per day fall from 9 to 6, a factor of 6/9 = 2/3. Shorter shifts lengthen the time, so the days get multiplied by the reciprocal 3/2.

  • Days = 25 × 4/5 × 3/2 = 30, which agrees with the man-hour computation.

The same work is therefore completed in 30 days.

Explore the full course: Ssc Cgl Tier 1

Loading lesson…