Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours…
2024
Working 9 hours a day, 12 persons complete a work in 25 days. Working 6 hours a day, 15 persons can do the same work in:
Answer: C. 30 days — ConceptWhen one and the same job is finished under two different working arrangements, the total amount of labour the job demands does not change. Measuring…
- A.
28 days
- B.
29 days
- C.
30 days
- D.
32 days
Attempted by 4 students.
Show answer & explanation
Correct answer: C
Concept
When one and the same job is finished under two different working arrangements, the total amount of labour the job demands does not change. Measuring that labour in man-hours turns this into a single invariant: persons × hours worked per day × days = total man-hours.
Hence M1H1D1 = M2H2D2. The number of days is inversely proportional to the product of the number of persons and the hours each of them works per day.
Application
First arrangement: 12 persons work 9 hours a day for 25 days.
Total work = 12 × 9 × 25 = 2700 man-hours. This total is fixed by the job itself, so it must also hold for the second arrangement.
Second arrangement: 15 persons work 6 hours a day, so together they supply 15 × 6 = 90 man-hours each day.
Let D be the number of days required. Equating the labour supplied to the labour demanded: 90 × D = 2700.
D = 2700 ÷ 90 = 30.
Cross-check
The same figure follows from proportionality alone, without ever computing the total.
Persons rise from 12 to 15, a factor of 15/12 = 5/4. More workers shorten the time, so the days get multiplied by the reciprocal 4/5.
Hours per day fall from 9 to 6, a factor of 6/9 = 2/3. Shorter shifts lengthen the time, so the days get multiplied by the reciprocal 3/2.
Days = 25 × 4/5 × 3/2 = 30, which agrees with the man-hour computation.
The same work is therefore completed in 30 days.