A and B can complete a work in 14 days and 24 days respectively. If A alone…

2026

A and B can complete a work in 14 days and 24 days respectively. If A alone works for 4 days, what fraction of work remains?

  1. A.

    5/7

  2. B.

    6/7

  3. C.

    13/7

  4. D.

    1/7

Attempted by 31 students.

Show answer & explanation

Correct answer: A

Step 1: Calculate A's daily work rate.
A can complete the work in 14 days, so A's 1 day's work = 1/14.

Step 2: Calculate work done by A in 4 days.
Work done by A in 4 days = 4 × (1/14) = 4/14 = 2/7.

Step 3: Calculate the remaining work.
Total work is considered as 1.
Remaining work = 1 - (Work done by A)
Remaining work = 1 - (2/7) = (7 - 2)/7 = 5/7.

Final Answer: Option 1