X and Y together can complete a work in 60 days. Y and Z together can complete…
2024
X and Y together can complete a work in 60 days. Y and Z together can complete the same work in 90 days. If X, Y and Z all work together, then the same work gets completed in 45 days. How many days will X and Z together take to complete the same work?
- A.
120 days
- B.
90 days
- C.
60 days
- D.
150 days
Attempted by 21 students.
Show answer & explanation
Correct answer: C
To solve this problem, we need to determine the work rates of each individual or pair. The work rate is the portion of the total work completed in one day.
Step-by-Step Calculation
Define the Work Rates:
Let the work rate of X be x, Y be y, and Z be z.
X + Y = 1/60 (rate per day)
Y + Z = 1/90 (rate per day)
X + Y + Z = 1/45 (rate per day)
Find the individual rate of Y:
First, add the rates of (X + Y) and (Y + Z):
(X + Y) + (Y + Z) = 1/60 + 1/90
X + 2Y + Z = 3/180 + 2/180 = 5/180 = 1/36
Now, subtract the trio's rate (X + Y + Z) from this sum to isolate Y:
(X + 2Y + Z) - (X + Y + Z) = 1/36 - 1/45
Y = 5/180 - 4/180 = 1/180 per day.
Find the combined rate of X + Z:
We know X + Y + Z = 1/45.
X + Z = (X + Y + Z) - Y
X + Z = 1/45 - 1/180
Convert to common denominator: 4/180 - 1/180 = 3/180 = 1/60 per day.
Calculate the time for X + Z:
Since X + Z complete 1/60 of the work in one day, they will take 60 days to complete the entire job.