X and Y together can complete a work in 60 days. Y and Z together can complete…

2024

X and Y together can complete a work in 60 days. Y and Z together can complete the same work in 90 days. If X, Y and Z all work together, then the same work gets completed in 45 days. How many days will X and Z together take to complete the same work?

  1. A.

    120 days

  2. B.

    90 days

  3. C.

    60 days

  4. D.

    150 days

Attempted by 21 students.

Show answer & explanation

Correct answer: C

To solve this problem, we need to determine the work rates of each individual or pair. The work rate is the portion of the total work completed in one day.

Step-by-Step Calculation
Define the Work Rates:

Let the work rate of X be x, Y be y, and Z be z.

X + Y = 1/60 (rate per day)

Y + Z = 1/90 (rate per day)

X + Y + Z = 1/45 (rate per day)

Find the individual rate of Y:

First, add the rates of (X + Y) and (Y + Z):
(X + Y) + (Y + Z) = 1/60 + 1/90
X + 2Y + Z = 3/180 + 2/180 = 5/180 = 1/36

Now, subtract the trio's rate (X + Y + Z) from this sum to isolate Y:
(X + 2Y + Z) - (X + Y + Z) = 1/36 - 1/45
Y = 5/180 - 4/180 = 1/180 per day.

Find the combined rate of X + Z:

We know X + Y + Z = 1/45.

X + Z = (X + Y + Z) - Y

X + Z = 1/45 - 1/180

Convert to common denominator: 4/180 - 1/180 = 3/180 = 1/60 per day.

Calculate the time for X + Z:

Since X + Z complete 1/60 of the work in one day, they will take 60 days to complete the entire job.

Explore the full course: Rssb Senior Computer Instructor