Two persons A and B complete a task in 15 days, when they work together.…

2023

Two persons A and B complete a task in 15 days, when they work together. Person A completes the task in 20 days if he works alone. How many days will B take to finish the task alone?

  1. A.

    35 days

  2. B.

    25 days

  3. C.

    60 days

  4. D.

    More than one of the above

  5. E.

    None of the above

Attempted by 56 students.

Show answer & explanation

Correct answer: C

Step 1: Let the total work be 1 unit. When A and B work together, they complete the work in 15 days. So, their combined work rate is 1/15 per day.

Step 2: A alone completes the work in 20 days. So, A's work rate is 1/20 per day.

Step 3: B's work rate = Combined rate - A's rate = 1/15 - 1/20.

Step 4: Calculate 1/15 - 1/20 = (4 - 3)/60 = 1/60. So, B's rate is 1/60 per day.

Step 5: Therefore, B alone will take 60 days to complete the work.

हिन्दी उत्तर:

चरण 1: कुल कार्य 1 इकाई मानें। A और B मिलकर 15 दिन में कार्य पूरा करते हैं। इसलिए, उनकी संयुक्त कार्य दर 1/15 प्रति दिन है।

चरण 2: A अकेले 20 दिन में कार्य पूरा करता है। इसलिए, A की कार्य दर 1/20 प्रति दिन है।

चरण 3: B की कार्य दर = संयुक्त दर - A की दर = 1/15 - 1/20।

चरण 4: 1/15 - 1/20 = (4 - 3)/60 = 1/60। इसलिए, B की दर 1/60 प्रति दिन है।

चरण 5: अतः, B अकेले कार्य पूरा करने में 60 दिन लेगा।