P and Q alone can do a work in 18 and 45 days respectively. They started the…

2021

P and Q alone can do a work in 18 and 45 days respectively. They started the work together and P left after 3 days of start of work. Q completed the remaining work. In how many days was the work completed?

  1. A.

    37.5

  2. B.

    39.5

  3. C.

    34

  4. D.

    36

Attempted by 59 students.

Show answer & explanation

Correct answer: A

Solution:

  • P's rate = 1/18 of the work per day. Q's rate = 1/45 of the work per day.

  • Combined rate = 1/18 + 1/45 = 7/90 of the work per day.

  • Work done in the first 3 days = 3 × 7/90 = 7/30 of the work.

  • Remaining work = 1 - 7/30 = 23/30 of the work.

  • Time for Q alone to finish remaining work = (23/30) ÷ (1/45) = (23/30) × 45 = 34.5 days.

  • Total time = initial 3 days + 34.5 days = 37.5 days.

Answer: 37.5 days.