A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would A take separately to do the same work?

  1. A.

    40 days
    40 दिन

  2. B.

    30 days
    30 दिन

  3. C.

    20 days
    20 दिन

  4. D.

    10 days
    10 दिन

Attempted by 5 students.

Show answer & explanation

Correct answer: B

Solution: Find A's time using work rates.

  • Let A, B, C denote the fractions of the work they do per day.

  • From the given: A + B = 1/12, B + C = 1/15, C + A = 1/20.

  • Add the three equations: 2(A + B + C) = 1/12 + 1/15 + 1/20 = 1/5, so A + B + C = 1/10.

  • Then A = (A + B + C) - (B + C) = 1/10 - 1/15 = 1/30.

  • So A does the whole work in 30 days.