A project is planned for an enterprise accounting system with an estimated…

PYQ UGC NET 2025

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

What is the estimated development time in months?

  1. A.

    28 Months

  2. B.

    26 Months

  3. C.

    34 Months

  4. D.

    12 Months