Given a project with an estimated effort of 1500 person-hours and a team of 5…
PYQ UGC NET 2024
Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project, if each person works 8 hours a day?
- A.
30
- B.
37.5
- C.
40
- D.
45.5