Given a project with an estimated effort of 1500 person-hours and a team of 5…

PYQ UGC NET 2024

Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project, if each person works 8 hours a day?

  1. A.

    30

  2. B.

    37.5

  3. C.

    40

  4. D.

    45.5