A project is planned for an enterprise accounting system with an estimated…
PYQ UGC NET 2025
A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )
Effort = 3.0 . (KLOC)1.0
Development time = 2.5 . (Effort)1/2
Average cost per person-month (pm) = $10,000
A contingency margin of 10% effort is mandatory
The client demands a detailed schedule if staff is capped at 15 engineers.
What is the initial effort in Person-month (PM) before adding the contingency margin?
- A.
240 PM
- B.
260 PM
- C.
180 PM
- D.
200 PM