A project is planned for an enterprise accounting system with an estimated…

2026

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

If the staff is capped at 15 engineers what is the revised calendar duration?

Answer: C. 13.2 MonthsFirst, calculate base effort as 3.0 multiplied by 60 KLOC to the power of 1.0, resulting in 180 person-months. Next, apply the mandatory 10% contingency…

  1. A.

    20.0 Months

  2. B.

    18.4 Months

  3. C.

    13.2 Months

  4. D.

    22.0 Months

Attempted by 67 students.

Show answer & explanation

Correct answer: C

First, calculate base effort as 3.0 multiplied by 60 KLOC to the power of 1.0, resulting in 180 person-months.

Next, apply the mandatory 10% contingency margin to get a total effort of 198 person-months.

Finally, divide the total effort by the capped staff of 15 engineers to find the revised calendar duration of 13.2 months.