A project is planned for an enterprise accounting system with an estimated…
PYQ UGC NET 2025
A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )
Effort = 3.0 . (KLOC)1.0
Development time = 2.5 . (Effort)1/2
Average cost per person-month (pm) = $10,000
A contingency margin of 10% effort is mandatory
The client demands a detailed schedule if staff is capped at 15 engineers.
If the staff is capped at 15 engineers what is the revised calendar duration?
- A.
20.0 Months
- B.
18.4 Months
- C.
13.2 Months
- D.
22.0 Months