A project is planned for an enterprise accounting system with an estimated…

PYQ UGC NET 2025

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

What is the implied average staffing level?

  1. 8 Engineers

  2. 5 Engineers

  3. 10 Engineers

  4. 12 Engineers