Given a project that uses the COCOMO model with an estimated effort of 2000…

PYQ UGC NET 2024

Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-month per KLOC, what is the estimated size of the project in KLOC?

  1. A.

    200

  2. B.

    400

  3. C.

    100

  4. D.

    50