Seven girls can do a piece of work in 13 days, six boys can do the same piece…

2022

Seven girls can do a piece of work in 13 days, six boys can do the same piece of work in 12 days, nine men can do the same piece of work in 9 days and six women can do the same piece of work in 14 days. Who are the most efficient?

  1. A.

    Boys

  2. B.

    Girls

  3. C.

    Women

  4. D.

    Men

Attempted by 4 students.

Show answer & explanation

Correct answer: A

Concept

Efficiency means work done per person per day, not the number of days a whole group takes. If a group of N people finishes one unit of work in D days, the team's combined person-days is N x D, and each individual's daily rate is 1 / (N x D). The smaller the value of N x D, the higher the individual efficiency.

Applying it to each group

  1. Girls: N x D = 7 x 13 = 91, so each girl's rate = 1/91 per day.

  2. Boys: N x D = 6 x 12 = 72, so each boy's rate = 1/72 per day.

  3. Men: N x D = 9 x 9 = 81, so each man's rate = 1/81 per day.

  4. Women: N x D = 6 x 14 = 84, so each woman's rate = 1/84 per day.

Cross-check

Cross-check: compare the person-day totals 91, 72, 81 and 84. The smallest total is 72, which gives the largest individual daily rate 1/72. Hence one boy does more work per day than one girl, one man or one woman, so boys are the most efficient.