6 men or 8 women can do a work in 25 days. The number of days required by 8…
2015
6 men or 8 women can do a work in 25 days. The number of days required by 8 men and 6 women to complete the work is
- A.
12
- B.
11
- C.
10
- D.
9
Show answer & explanation
Correct answer: A
When two groups can each finish the very same job in the very same number of days, their total daily outputs must be equal — this equality is what fixes the ratio between one individual's daily work in one group and one individual's daily work in the other group. That per-person efficiency ratio, combined with the job's total size, is what then decides how long any differently composed team needs for the same job.
Let one man's one-day work be m and one woman's one-day work be w.
Since 6 men finish the job in 25 days and 8 women finish the same job in 25 days, both groups produce the same total work: 6m × 25 = 8w × 25, so 6m = 8w, i.e. m : w = 4 : 3.
Write the job as 24 units (the LCM of 6 and 8). Then 6 men completing 24 units in 25 days gives 1 man's daily work = 24 ÷ (6 × 25) = 4/25 unit; 8 women completing 24 units in 25 days gives 1 woman's daily work = 24 ÷ (8 × 25) = 3/25 unit — consistent with the 4 : 3 ratio.
The new team of 8 men and 6 women therefore does 8 × 4/25 + 6 × 3/25 = 32/25 + 18/25 = 50/25 = 2 units per day.
Days required = total work ÷ daily rate = 24 ÷ 2 = 12 days.
Cross-checking with the man-equivalent route: since 1 woman = 3/4 man (from the 4 : 3 ratio), 8 men and 6 women equal 8 + 6 × 3/4 = 12.5 man-equivalents. The whole job equals 6 men's 25-day output, i.e. 6 × 25 = 150 man-days. So the new team needs 150 ÷ 12.5 = 12 days — the same result.
So the work is completed in 12 days.