A and B can do a work in 21 days. A is 7/4 times as efficient as B. In how…

2020

A and B can do a work in 21 days. A is 7/4 times as efficient as B. In how many days, A alone can complete the 200/3 % of the work?

  1. A.

    22

  2. B.

    33

  3. C.

    36

  4. D.

    27

Attempted by 47 students.

Show answer & explanation

Correct answer: A

Given:
A and B together complete the work in 21 days.
Efficiency ratio:
A : B = 7 : 4
Let efficiencies be:
7x and 4x
Combined efficiency:
= 11x
Since total work is completed in 21 days:
11x = 1/21
x = 1/231
Efficiency of A:
= 7x
= 7/231
= 1/33
So, A alone completes 1 unit of work in 33 days.
Now,
Required work = 200/3 %
= 200/3 × 1/100
= 2/3 of the work
Time taken by A to complete 2/3 work:
= 33 × 2/3
= 22 days