Consider the given schedule
R1(X), R2(Z), R1(Z), R3(X), R3(Y), W1(X), Commit1, W3(Y), Commit3, R2(Y), W2(Z), W2(Y), Commit2. The given schedule is
- A.
Recoverable only
- B.
Cascade less only
- C.
recoverable and cascade-less
- D.
None