Consider the following schedule ‘S’.  

S: r1(X); r2(Z); r3(X); r1(Z); r2(Y); r3(Y); w1(X); c1; w2(Z); w3(Y); w2(Y); c3; c2; 

The schedule ‘S’ is

  1. A.

    Recoverable

  2. B.

    Cascade less

  3. C.

    recoverable and cascade-less

  4. D.

    None