Ramesh alone can complete a work in 24 days. Ramesh and Somesh can complete it in 8 days. How long will Somesh alone take to complete the work?
- A.
10 days
- B.
15 days
- C.
14 days
- D.
12 days
Attempted by 26 students.
Show answer & explanation
Correct answer: D
Ramesh's work rate is 1/24 per day. Together they work at 1/8 per day, so Somesh's rate is 1/8 - 1/24 = 1/12 per day. Hence Somesh alone takes 12 days.