A is able to complete a task in 15 days, while B takes 20 days to finish the same task. If they collaborate and work together for 4 days, what fraction of the work will still remain?

  1. A.

    1/3

  2. B.

    7/15

  3. C.

    8/15

  4. D.

    4/9

Attempted by 4 students.

Show answer & explanation

Correct answer: C

1. (A+B)'s 1 day work = 1/15 + 1/20 = 7/60. 2. 4 days work = 4 * 7/60 = 28/60 = 7/15. 3. Remaining = 1 - 7/15 = 8/15.