X and Y together can complete a work in 60 days. Y and Z together can complete…

2024

X and Y together can complete a work in 60 days. Y and Z together can complete the same work in 90 days. If X, Y and Z all work together, then the same work gets completed in 45 days. How many days will X and Z together take to complete the same work?

Answer: C. 60 daysTo solve this problem, we need to determine the work rates of each individual or pair. The work rate is the portion of the total work completed in one day.…

  1. A.

    120 days

  2. B.

    90 days

  3. C.

    60 days

  4. D.

    150 days

Attempted by 101 students.

Show answer & explanation

Correct answer: C

To solve this problem, we need to determine the work rates of each individual or pair. The work rate is the portion of the total work completed in one day.

Step-by-Step Calculation
Define the Work Rates:

Let the work rate of X be x, Y be y, and Z be z.

X + Y = 1/60 (rate per day)

Y + Z = 1/90 (rate per day)

X + Y + Z = 1/45 (rate per day)

Find the individual rate of Y:

First, add the rates of (X + Y) and (Y + Z):
(X + Y) + (Y + Z) = 1/60 + 1/90
X + 2Y + Z = 3/180 + 2/180 = 5/180 = 1/36

Now, subtract the trio's rate (X + Y + Z) from this sum to isolate Y:
(X + 2Y + Z) - (X + Y + Z) = 1/36 - 1/45
Y = 5/180 - 4/180 = 1/180 per day.

Find the combined rate of X + Z:

We know X + Y + Z = 1/45.

X + Z = (X + Y + Z) - Y

X + Z = 1/45 - 1/180

Convert to common denominator: 4/180 - 1/180 = 3/180 = 1/60 per day.

Calculate the time for X + Z:

Since X + Z complete 1/60 of the work in one day, they will take 60 days to complete the entire job.