A man X can complete \(\frac{1}{3}\) of a job in 5 days and another man Y can…

2023

A man X can complete \(\frac{1}{3}\) of a job in 5 days and another man Y can complete \(\frac{2}{5}\) of the job in 10 days. In how many days can both X and Y together complete the job?

Answer: A. \(9\frac{3}{8}\)ConceptA worker’s daily work rate equals the fraction of the job completed divided by the time taken. For people working together, add their daily rates; the…

  1. A.

    \(9\frac{3}{8}\)

  2. B.

    \(8\frac{3}{8}\)

  3. C.

    \(9\frac{3}{5}\)

  4. D.

    \(7\frac{7}{9}\)

Show answer & explanation

Correct answer: A

Concept

A worker’s daily work rate equals the fraction of the job completed divided by the time taken.

For people working together, add their daily rates; the completion time is the reciprocal of the combined rate.

Application

  1. X’s rate is \(\frac{1}{3}\) ÷ 5 = \(\frac{1}{15}\) of the job per day.

  2. Y’s rate is \(\frac{2}{5}\) ÷ 10 = \(\frac{1}{25}\) of the job per day.

  3. Their combined rate is \(\frac{1}{15}+\frac{1}{25}=\frac{5+3}{75}=\frac{8}{75}\) of the job per day.

  4. Thus, the required time is \(1÷\frac{8}{75}=\frac{75}{8}=9\frac{3}{8}\) days.

Cross-check

In \(\frac{75}{8}\) days, X completes \(\frac{5}{8}\) of the job and Y completes \(\frac{3}{8}\); together these fractions make one whole job.

Result

Therefore, both X and Y together complete the job in \(9\frac{3}{8}\) days.

Explore the full course: Nta Ugc Net Paper 1

Loading lesson…