Mohan can do a piece of work in 7 days working 9 hours a day and Shyam can do the same work in 6 days working 7 hours a day. How long will they take to complete the job working together 8\frac{2}{5}​ hours a day?

  1. A.

    3 days

  2. B.

    4 days

  3. C.

    3½ days

  4. D.

    5 days

Attempted by 9 students.

Show answer & explanation

Correct answer: A

Mohan takes 7 days × 9 hours = 63 hours. Shyam takes 6 days × 7 hours = 42 hours. Combined hourly rate: 1/63 + 1/42 = 5/126. Daily work at 8 2/5 hours (42/5 hours): (5/126) × (42/5) = 1/3. Total days needed: 1 ÷ (1/3) = 3 days.