A can do a certain work in 12 days, and B alone can do the same work in 16…

20202020

A can do a certain work in 12 days, and B alone can do the same work in 16 days. A and B undertook to complete it for Rs. 8000. With the help of C, they completed the work in 6 days. How much money (in Rs.) should be paid to C?

  1. A.

    1000

  2. B.

    2000

  3. C.

    3000

  4. D.

    4000

Attempted by 50 students.

Show answer & explanation

Correct answer: A

Given:

  • A can complete the work in 12 days

  • B can complete the work in 16 days

  • Total payment = Rs. 8000

  • With the help of C, the work is completed in 6 days

Step 1: Find efficiencies of A and B

Efficiency of A:
= 1/12 work per day
Efficiency of B:
= 1/16 work per day
Combined efficiency of A and B:
1/12 + 1/16
Taking LCM = 48
= 4/48 + 3/48
= 7/48

Step 2: Find total efficiency with C

Since the work is completed in 6 days:
Total efficiency of A + B + C
= 1/6
Efficiency of C:
= 1/6 − 7/48
Taking LCM = 48
= 8/48 − 7/48
= 1/48

Step 3: Find C’s share of money

Total work is divided according to efficiencies.
Ratio of efficiencies:
A : B : C
= 1/12 : 1/16 : 1/48
Multiplying by 48:
= 4 : 3 : 1
Total ratio:
4 + 3 + 1 = 8
C’s share:
= (1/8) × 8000
= 1000