A, B and C together can complete 66⅔ % of work in 2 days and A & B together…
2023
A, B and C together can complete 66⅔ % of work in 2 days and A & B together can complete 30% of the work in 3 days. Find the time taken by C alone to complete 4⅔ of total work.
- A.
20 days
- B.
15 days
- C.
7.5 days
- D.
5 days
- E.
12 days
Attempted by 1 students.
Show answer & explanation
Correct answer: A
Concept
In work-and-time problems, each worker (or group) has a constant daily work rate equal to the fraction of the job they finish per day. Rates add: if a combined group's rate is known and one sub-group's rate is known, an individual's rate is the difference. Time to finish any amount of work equals that amount divided by the rate.
Application
Convert the given completions to rates. A + B + C finish 66⅔% = 2/3 of the work in 2 days, so their combined rate is (2/3) ÷ 2 = 1/3 of the work per day.
A + B finish 30% = 3/10 of the work in 3 days, so their combined rate is (3/10) ÷ 3 = 1/10 of the work per day.
C's own rate is the difference: 1/3 − 1/10 = 10/30 − 3/30 = 7/30 of the work per day.
The required amount is 4⅔ = 14/3 (in units of one whole job). Time = work ÷ rate = (14/3) ÷ (7/30) = (14/3) × (30/7) = 20 days.
Cross-check
Verify by multiplying back: in 20 days C does 20 × 7/30 = 140/30 = 14/3 of the job, which is exactly 4⅔. The rate split is also consistent because 1/10 (for A+B) is less than 1/3 (for A+B+C), so C contributes a positive rate of 7/30, as required.