Suppose there are 5 processes P1, P2, P3, P4 and P5 with processing time requirements 10, 6, 2, 4 and 8 respectively. What is the average completion time if SJF (Shortest Job First) policy is used ?

  1. A.

    10

  2. B.

    12

  3. C.

    14

  4. D.

    16

Attempted by 47 students.

Show answer & explanation

Correct answer: C

1. Sort processes by burst time: P3(2), P4(4), P2(6), P5(8), P1(10). 2. Calculate completion times: P3=2, P4=6, P2=12, P5=20, P1=30. 3. Sum completion times: 70. 4. Average = 70/5 = 14.