Requirements prioritization and negotiation belongs to :

2015

Requirements prioritization and negotiation belongs to :

Answer: B. Requirements elicitationAnswer: Requirements elicitation Why this is correct: Prioritization and negotiation are performed while gathering and agreeing requirements with stakeholders…

  1. A.

    Requirements validation

  2. B.

    Requirements elicitation

  3. C.

    Feasibility study

  4. D.

    Requirements reviews

Attempted by 475 students.

Show answer & explanation

Correct answer: B

Answer: Requirements elicitation

Why this is correct: Prioritization and negotiation are performed while gathering and agreeing requirements with stakeholders to resolve conflicts and determine which requirements are most important.

  • Key activities in elicitation: stakeholder interviews, workshops, negotiation, and prioritization techniques (for example, MoSCoW, ranking).

  • Feasibility studies evaluate whether a solution is viable technically, economically, or operationally, but they do not primarily perform stakeholder negotiation of requirements.

  • Validation and reviews check that requirements are correct, complete, and testable after they have been captured; they focus on quality rather than negotiating priorities.

Memory aid: elicitation = collect and agree; validation = confirm; feasibility = can we; reviews = quality check.