P can do a piece of work in 5 days of 8 hours each and Q can do in 4 days of 6…

2023

P can do a piece of work in 5 days of 8 hours each and Q can do in 4 days of 6 hours each. How long will they take do it working 5 hours a day?

  1. A.

    2 days

  2. B.

    3 days

  3. C.

    4 days

  4. D.

    5 days

Attempted by 44 students.

Show answer & explanation

Correct answer: B

Solution:

  • Step 1: Compute total hours for each worker. P: 5 × 8 = 40 hours (rate = 1/40 job per hour). Q: 4 × 6 = 24 hours (rate = 1/24 job per hour).

  • Step 2: Find combined hourly rate. 1/40 + 1/24 = 1/15 job per hour.

  • Step 3: Calculate work done per day at 5 hours/day. 5 × 1/15 = 1/3 of the job per day.

  • Step 4: Determine number of days required. 1 ÷ (1/3) = 3 days. Answer: 3 days.