Lita can complete the project in 15 days, Babita can complete the same project…

2023

Lita can complete the project in 15 days, Babita can complete the same project in 20 days. Calculate the time needed to complete the same project if they work together on it?

  1. A.

    60/7

  2. B.

    40/8

  3. C.

    20/3

  4. D.

    11/16

Show answer & explanation

Correct answer: A

Concept: When two people work on the same task, each person's work rate is 1 ÷ (days needed alone). Working together, their daily rates simply add, and the time to finish together is the reciprocal of that combined rate.

Application:

  1. Lita's work rate = 1/15 of the project per day (since she alone takes 15 days).

  2. Babita's work rate = 1/20 of the project per day (since she alone takes 20 days).

  3. Combined daily rate = 1/15 + 1/20 = 4/60 + 3/60 = 7/60 of the project per day.

  4. Time needed together = 1 ÷ (7/60) = 60/7 days.

Cross-check: In 60/7 days at a combined rate of 7/60 per day, the work done = (60/7) × (7/60) = 1, i.e. the whole project — confirming the value. This also fits the expected range: since Lita (the faster worker) alone needs 15 days, two people working together must take somewhere between half that (7.5 days) and the full 15 days; 60/7 ≈ 8.57 days sits inside that range.

So Lita and Babita together complete the project in 60/7 days.

Explore the full course: Deloitte Nla