Mohan can do a bit of work in 25 days which can be completed by Sohan in 20…

2023

Mohan can do a bit of work in 25 days which can be completed by Sohan in 20 days. Both together labour for 5 days and afterward Mohan leaves off. How long will Sohan take to complete the remaining work?

Answer: B. 11 daysStep 1: Mohan's work rate = 1/25 per day. Sohan's work rate = 1/20 per day. Step 2: Combined work rate = 1/25 + 1/20 = (4 + 5)/100 = 9/100 per day. Step 3:…

  1. A.

    20 days

  2. B.

    11 days

  3. C.

    14 days

  4. D.

    More than one of the above

  5. E.

    None of the above

Attempted by 110 students.

Show answer & explanation

Correct answer: B

Step 1: Mohan's work rate = 1/25 per day. Sohan's work rate = 1/20 per day.

Step 2: Combined work rate = 1/25 + 1/20 = (4 + 5)/100 = 9/100 per day.

Step 3: Work done in 5 days = 5 × 9/100 = 45/100 = 9/20.

Step 4: Remaining work = 1 - 9/20 = 11/20.

Step 5: Time for Sohan to complete remaining work = (11/20) / (1/20) = 11 days.

हिन्दी उत्तर:

चरण 1: मोहन की कार्य दर = 1/25 प्रति दिन। सोहन की कार्य दर = 1/20 प्रति दिन।

चरण 2: संयुक्त कार्य दर = 1/25 + 1/20 = (4 + 5)/100 = 9/100 प्रति दिन।

चरण 3: 5 दिनों में किया गया कार्य = 5 × 9/100 = 45/100 = 9/20।

चरण 4: शेष कार्य = 1 - 9/20 = 11/20।

चरण 5: शेष कार्य पूरा करने में सोहन को लगने वाला समय = (11/20) / (1/20) = 11 दिन।