Rajesh, in his printing press, got an order to print some books, out of which he completed 17/27 of the order in 34 days. In how many days did he complete the entire order of printing?

  1. A.

    60

  2. B.

    20

  3. C.

    54

  4. D.

    56

Attempted by 57 students.

Show answer & explanation

Correct answer: C

Understand the Relationship:
Rajesh completed 17/27 of the order in 34 days. This means that 17 parts of the work took 34 days to finish.

Determine the Rate:
If 17 parts take 34 days, we can find out how long one part takes:
One part = 34 days / 17 = 2 days per part.

Calculate Total Time:
The entire order consists of 27 parts. Since each part takes 2 days:
Total time = 27 parts * 2 days/part = 54 days.