“System Requirements Specification (SRS)” document is prepared by the System…
2024
“System Requirements Specification (SRS)” document is prepared by the System Analyst at the end of __________ phase of System Development Life Cycle.
- A.
Systems Design
- B.
Systems Implementation
- C.
Preliminary Investigation
- D.
Systems Requirement Analysis
- E.
Question not attempted
Attempted by 18 students.
Show answer & explanation
Correct answer: D
The SRS is prepared after requirements have been analyzed and documented. Therefore it is prepared at the end of the systems requirement analysis phase.