Which of the following is NOT a step of requirement engineering?

2026

Which of the following is NOT a step of requirement engineering?

  1. A.

    Requirement design

  2. B.

    Requirement documentation

  3. C.

    Requirement analysis

  4. D.

    Requirement elicitation

Attempted by 107 students.

Show answer & explanation

Correct answer: A

Standard requirement engineering processes consist of elicitation, analysis, specification (documentation), and validation. Requirement design is categorized under the system design phase rather than requirement engineering.