Which of the following activities does not belong to implementation phase of…

2018

Which of the following activities does not belong to implementation phase of SDLC?

  1. A.

    Program testing

  2. B.

    File conversion

  3. C.

    User training

  4. D.

    New changes to the system

Attempted by 671 students.

Show answer & explanation

Correct answer: D

The implementation phase of SDLC includes activities like program testing, file conversion, and user training. New changes to the system are part of the maintenance phase, not implementation.