Which of the following activities does not belong to implementation phase of SDLC?
- A.
Program testing
- B.
File conversion
- C.
User training
- D.
New changes to the system
Attempted by 671 students.
Show answer & explanation
Correct answer: D
The implementation phase of SDLC includes activities like program testing, file conversion, and user training. New changes to the system are part of the maintenance phase, not implementation.