Project risk factor is considered in —

2018

Project risk factor is considered in —

  1. A.

    waterfall model

  2. B.

    prototyping model

  3. C.

    spiral model

  4. D.

    iterative enhancement model

Attempted by 982 students.

Show answer & explanation

Correct answer: C

The spiral model is explicitly risk-driven. Each iteration begins with identifying, analyzing, and resolving project risks, making risk assessment its core feature.