Project risk factor is considered in —

2018

Project risk factor is considered in —

Answer: C. spiral modelThe spiral model is explicitly risk-driven. Each iteration begins with identifying, analyzing, and resolving project risks, making risk assessment its core…

  1. A.

    waterfall model

  2. B.

    prototyping model

  3. C.

    spiral model

  4. D.

    iterative enhancement model

Attempted by 1266 students.

Show answer & explanation

Correct answer: C

The spiral model is explicitly risk-driven. Each iteration begins with identifying, analyzing, and resolving project risks, making risk assessment its core feature.