Arrange the following stages of the prototyping software-development model in…
2025
Arrange the following stages of the prototyping software-development model in the correct sequence.
A. Start
B. Develop Prototype
C. Deliver to customer
D. Quick Design
E. Quick Plan
Choose the correct answer from the options given below.
Answer: B. A, E, D, B, C — ConceptA prototyping cycle separates rapid planning, quick design, prototype construction, and customer delivery. Each later activity uses the output of the…
- A.
A, B, C, D, E
- B.
A, E, D, B, C
- C.
A, B, D, E, C
- D.
A, B, E, D, C
Attempted by 456 students.
Show answer & explanation
Correct answer: B
Concept
A prototyping cycle separates rapid planning, quick design, prototype construction, and customer delivery. Each later activity uses the output of the activity before it.
The quick plan establishes scope, the quick design provides a lightweight blueprint, construction turns that design into a prototype, and delivery exposes the prototype to the customer for evaluation.
Application
A. Start initiates the prototyping cycle and establishes the need to be explored.
E. Quick Plan identifies the immediate scope and features for the prototype.
D. Quick Design sketches the user-visible aspects and structure needed for construction.
B. Develop Prototype builds the working model from that quick design.
C. Deliver to customer presents the prototype for evaluation and feedback.
Cross-check
A, B, C, D, E attempts construction and delivery before planning and design.
A, B, D, E, C attempts construction before the quick plan and quick design.
A, B, E, D, C also attempts construction before planning and design.
Therefore, the dependency-preserving sequence is A, E, D, B, C.