An _______ chart is a project schedule representation that presents project…

2019

An _______ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ________ tasks and it defines project ________.

  1. A.

    Activity, Shortest, Independent, Cost

  2. B.

    Activity, Longest, Dependent, Duration

  3. C.

    Activity, Longest, Independent, Duration

  4. D.

    Activity, Shortest, Dependent, Duration

Attempted by 37 students.

Show answer & explanation

Correct answer: B

Correct completion: Activity, Longest, Dependent, Duration

Explanation:

  • Activity chart: a project schedule shown as a directed graph where activities (tasks) are nodes and arrows represent precedence relationships.

  • Critical path: the longest sequence of dependent tasks (tasks linked by precedence with no slack).

  • Project duration: the critical path determines the minimum time needed to complete the project. Any delay to a task on the critical path delays the entire project.

  • Key takeaway: the correct phrase fills are Activity (chart), Longest, Dependent, Duration.