In a 5-stage pipeline, branch is resolved in EX stage. If branch frequency =…

2026

In a 5-stage pipeline, branch is resolved in EX stage. If branch frequency = 15% and misprediction penalty = 2 cycles, what is pipeline CPI?

Answer: A. 1.3Concept: In a pipelined processor achieving an ideal one-cycle-per-instruction throughput, the baseline CPI is 1. Any instruction that forces the pipeline to…

  1. A.

    1.3

  2. B.

    1.2

  3. C.

    1.1

  4. D.

    1.4

Attempted by 77 students.

Show answer & explanation

Correct answer: A

Concept: In a pipelined processor achieving an ideal one-cycle-per-instruction throughput, the baseline CPI is 1. Any instruction that forces the pipeline to stall raises the effective CPI above this baseline. A branch instruction whose outcome is not known until a later pipeline stage forces the pipeline to stall for a fixed number of cycles on every occurrence; this fixed per-branch stall cost is the branch (misprediction) penalty. Since the item supplies only a single branch frequency and a single fixed penalty value, with no separate misprediction-rate figure, the standard convention for this class of numerical is to apply that penalty uniformly to every branch instruction encountered. Averaged over all instructions, the overall CPI is: CPI = Ideal CPI + (Branch Frequency x Branch Penalty).

Application:

  1. Identify the given quantities: ideal CPI = 1 (one instruction completes per cycle in a hazard-free pipeline); branch frequency = 15% = 0.15 (fraction of instructions that are branches); branch penalty = 2 cycles (stall cycles incurred per branch, since the outcome is known only in the EX stage).

  2. Compute the average stall contributed by branch instructions: Stall per instruction = Branch Frequency x Branch Penalty = 0.15 x 2 = 0.30 cycles.

  3. Add this stall contribution to the ideal CPI: CPI = 1 + 0.30 = 1.30.

Cross-check with a per-100-instruction count: out of 100 instructions, 15 are branches; each branch adds 2 stall cycles, giving 15 x 2 = 30 extra cycles; total cycles = 100 (base) + 30 (stalls) = 130 cycles; CPI = total cycles / total instructions = 130 / 100 = 1.3, which matches the formula result.

Hence, the pipeline CPI is 1.3.