A alone can finish a work in 10 days and B alone can do it in 15 days. If they…

2025

A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish , the out of the total wages of Rs. 75. A will get -

  1. A.

    Rs. 30

  2. B.

    Rs 37.50

  3. C.

    Rs 45

  4. D.

    Rs 50

Attempted by 880 students.

Show answer & explanation

Correct answer: C

Solution: Find A's share of Rs.75 when A alone finishes in 10 days and B alone in 15 days.

  • Step 1: Compute individual work rates. A's rate = 1/10 work per day. B's rate = 1/15 work per day.

  • Step 2: Find the ratio of work done in the same time: 1/10 : 1/15 = 3 : 2.

  • Step 3: Split the wages in the ratio 3:2. A's share = 3/(3+2) × 75 = 3/5 × 75 = Rs.45.

Common mistake: Using the time-taken ratio (10:15) directly is wrong because wages depend on amount of work done (rates), not time taken. The correct approach uses the inverse relationship between time and work rate.